Jokeri Light Rail contact lines installed in March
Construction of the Jokeri Light Rail system is nearing completion in Otaniemi. Currently on winter break, work will resume in March with installation of contact lines between Maarintie and Otaniementie.
Work this week (Week 9) begins with snow removal. Contact line installations will start during Week 10 and include setting electrical cross-arms and stringing overhead cables. Construction will occur on day shifts and on night shifts, depending on the work phase. Caution should be exercised when near the work area as heavy machinery and equipment will be moving along the tracks from Maarintie all the way to Otaniementie. The work will not result in significant noise.
The contact line work is scheduled to last until Week 13.
Additional information
Jokeri Light Rail
Text: Jokeri Light Rail
Read more news
Welcome to Language Day Nov 5th at 11:30!
Come and find out what kind of language courses we offer at the Language Centre, meet our teachers and chat with them, get your hands on some student overall badges, and play games to test your language skills!
UniSport services at Aalto University facilities in autumn 2026
UniSport services for students and staffWebinar series on neurodiversity: Recording of the second webinar is available until 10.11.2026
The webinar series consists of three webinars during autumn 2026, focusing on the neurodiversity in higher education and work life.This English-language three-part webinar series explores how neurodiversity can be better understood and transformed into a strength for individuals, teams, and organizations.