Jokeri Light Rail contact lines installed in March
Construction of the Jokeri Light Rail system is nearing completion in Otaniemi. Currently on winter break, work will resume in March with installation of contact lines between Maarintie and Otaniementie.
Work this week (Week 9) begins with snow removal. Contact line installations will start during Week 10 and include setting electrical cross-arms and stringing overhead cables. Construction will occur on day shifts and on night shifts, depending on the work phase. Caution should be exercised when near the work area as heavy machinery and equipment will be moving along the tracks from Maarintie all the way to Otaniementie. The work will not result in significant noise.
The contact line work is scheduled to last until Week 13.
Additional information
Jokeri Light Rail
Text: Jokeri Light Rail
Read more news
New podcast explores Finnish contributions to artificial intelligence
Researchers Arno Solin ja Eric Malmi interview pioneers, entrepreneurs and experts about the AI field's history, disruptive consequences and the probability of humanity's destruction.
The company established by three anthropologists relied on strong research expertise
Etnografinen tutkimustoimisto Kenno Oy was established in 2014 when its three founders were finalising their master's degree studies at the University of Helsinki and wanted to create an interesting job for themselves.
The idea of three researchers generated a deep tech company
Sim Analytics Oy relies on strong research expertise. Its story began when three researcher colleagues working in different laboratories at LUT University began to consider how to provide and analyse data in a way that would support industrial companies in making business decisions.