Jokeri Light Rail contact lines installed in March
Construction of the Jokeri Light Rail system is nearing completion in Otaniemi. Currently on winter break, work will resume in March with installation of contact lines between Maarintie and Otaniementie.
Work this week (Week 9) begins with snow removal. Contact line installations will start during Week 10 and include setting electrical cross-arms and stringing overhead cables. Construction will occur on day shifts and on night shifts, depending on the work phase. Caution should be exercised when near the work area as heavy machinery and equipment will be moving along the tracks from Maarintie all the way to Otaniementie. The work will not result in significant noise.
The contact line work is scheduled to last until Week 13.
Additional information
Jokeri Light Rail
Text: Jokeri Light Rail
Read more news
Apply Now: Unite! Visiting Professorships at TU Graz
TU Graz, Austria, invites experienced postdoctoral researchers to apply for two fully funded visiting professorships. The deadline for expressions of interest is 20 February 2026, and the positions will begin on 1 October 2026.
A Bloc becomes a “living lab” for Aalto students: Entrepreneurial Futures course and Cafetoria join forces in pop-up collaboration
A Bloc’s pop-up space turned into a hands-on learning environment when Entrepreneurial Futures course and Cafetoria co-created a pop-up.
Outi Elina Kansanen leaves room for imperfections
In the 100 words series, the Development Manager at the School of Electrical Engineering shares how she has promoted equality, diversity and inclusion at Aalto