News

Construction of Jokeri Light Rail will start 3 June at Maarintie

The construction is prepared by tree felling in May.
Raide-Jokeri havainnekuva Ainonaukio, Otaniemi Kuva: Raide-Jokeri
Illustration of Otaniemi. Image: Raide-Jokeri

The construction of the Jokeri Light Rail is under preparation in May, so that construction can begin as early as possible in June. Preparatory work includes tree felling at Maarintie and Vaisalantie, and in Helsinki, west of Patterimäki. Trees will be felled following the new light railway and street alignments, and at Patterimäki following a new escape route. The felling areas are designed precisely so that the crashes are done only to the extent necessary.

In Otaniemi, south of Maarintie's current pedestrian and bicycle path, trees are felled for about 250 meters following the new alignment of the street. At the northern end of Vaisalantie, trees are felled according to the light railway line and a few individual trees around the site. The felling of trees begins on week 21 and will be completed in May. The work is carried out by a subcontractor of the Raide-Jokeri Alliance.

Raide-Jokeri aikataulu Kuva: Raide-Jokeri
Jokeri Light Rail's construction schedule. Image: Raide-Jokeri

The construction will begin at Maarintie in June

Construction will start in the coming summer in 22 different locations in Helsinki and Espoo. The duration of work at different sites varies from one year to four years. Construction begins with preparatory work, such as  work traffic arrangements and preparation of construction site support areas. Trees and surface soil are removed in some places, as well as new water supply lines are built.

The construction of high-speed railways will start in Espoo on Monday, 3 June at Maarintie and Ravitie.

After setting up the temporary road changes, Maarintie will be the first to perform topsoil removal, soil profiling and bottom reinforcement work. In addition, the ground cabling work on the 110 kilovolt transmission line, which has been ongoing since last autumn in Laajalahti, east of Kehä I, will continue until October.

During June, work will begin in a total of 13 different locations and in August in nine new sites. The impact of construction work for the coming summer, including traffic, will be communicated in more detail during May.

Contruction will begin in nine new sites in July-August

In late summer, the construction work that has already started will continue and work will begin in nine new sites. In Espoo, construction will begin in July-August at Maarinrannantie, Tietotie Konemiehentie, Linnoitustie and the new Impilahdensilta crossing Turunväylä. In Helsinki, the works will move to Pitäjänmäentie from the Pajamäentie junction towards the east.

More information
Jokeri Light Rail

  • Published:
  • Updated:
Share
URL copied!

Read more news

Raide-jokeri logo
Campus Published:

Night work at Raide-Jokeri construction site during July

Night work will be done at Raide-Jokeri construction site during July
Crystal Flowers exhibition Collineation Grounds. Photo: Mikko Raskinen.
Campus, Studies Published:

Persistent students created an exhibition combining math and art despite exceptional circumstances

The sheltered courtyard next to the main lobby of the Undergraduate Centre and its dark-red brick, black granite and copper clad façade provides a solid frame for the 2021 exhibition, Collineations grounds.
K3 building in the summer
Campus Published:

Check out the Aalto University Works K3 site online

A Webcam has been installed to the Aalto Works K3 site to follow the real-time situation. The site has been started up during the spring 2021.
Asko ja Else-Maj Harmia Aalto-yliopisto Töölön juhlasalissa
Campus Published:

‘The building designed by my father and Woldemar Baeckman really is magnificent’

Asko Harmia, the son of architect Hugo Harmia, visited the former School of Business building designed by his father and Woldemar Baeckman.