Construction of Jokeri Light Rail 75% complete – rail construction progressing ahead of schedule

The construction of Jokeri Light Rail has proceeded ahead of schedule. The rapid pace of construction now means that the light rail line can start operating about five months earlier than planned, i.e. early 2024. The construction in the Espoo section will mostly be finished in 2021.
Raide-Jokeri
Image: Jokeri Light Rail

Of the construction of Jokeri Light Rail, 75 per cent is now completed. We reached the milestone of three quarters at the end of October 2021. Rail construction has progressed ahead of schedule, and 21 kilometres of the 25-kilometre rails are now finished. 

The original target was having completed 20 kilometres of the rails by the end of 2021. Expectations were exceeded thanks to successful resourcing, coordination of schedules, and developing working methods. Most of the construction in the Espoo section will be completed in 2021, while the construction of the Keilaniemi terminus will continue in 2022. The installation of the overhead cables and finishing touches both on the line and the power supply stations will continue in Espoo in 2022.

In 2023, we will add the finishing touches to the Jokeri Light Rail worksites. We will also run commissioning tests and test traffic. The operation on the light rail should start in January 2024.

Text by Jokeri Light Rail

More information
Jokeri Light Rail webpages

Konemiehentie.jpg

HSY's contstruction site remains in place on Konemiehentie

Exception routes in the Konemiehentie - Sähkömiehentie area will continue until the end of November 2021. Exceptional route arrangements will also remain in place until the site is completed.

Kartta liikennejärjestelyistä2.jpg

Konemiehentie between Puumiehenkuja - Sähkömiehentie is closed until the end of November 2021.

  • Updated:
  • Published:
Share
URL copied!

Read more news

Isabel Salmi
University Published:

Isabel Salmi creates space for the opinions of quieter group members

In the 100 words series, the third-year student of Information Technology shares how she has promoted equality, diversity and inclusion at Aalto
Text 'Otaniemi on a sustainable path' and image of two people walking on campus.
Campus, Cooperation, Studies, University Published:

Make May the month of movement!

Take part in events on campus and make sustainable mobility part of your working or study day.
A-logo on campus
University Published:

Canvas learning platform data breach – There may be users at Aalto

If you have used Canvas, notify security@aalto.fi. As a precaution, you can also change your Aalto password.
freestyle-hiihtäjä Kuura Koivisto
Awards and Recognition, University Published:

Aalto University supports the combining of elite sport and studies – a quality label was awarded by the Olympic Committee

The audit team praised personalised study planning, flexible study paths and guidance related to a dual career