Construction of Jokeri Light Rail 75% complete – rail construction progressing ahead of schedule

The construction of Jokeri Light Rail has proceeded ahead of schedule. The rapid pace of construction now means that the light rail line can start operating about five months earlier than planned, i.e. early 2024. The construction in the Espoo section will mostly be finished in 2021.
Raide-Jokeri
Image: Jokeri Light Rail

Of the construction of Jokeri Light Rail, 75 per cent is now completed. We reached the milestone of three quarters at the end of October 2021. Rail construction has progressed ahead of schedule, and 21 kilometres of the 25-kilometre rails are now finished. 

The original target was having completed 20 kilometres of the rails by the end of 2021. Expectations were exceeded thanks to successful resourcing, coordination of schedules, and developing working methods. Most of the construction in the Espoo section will be completed in 2021, while the construction of the Keilaniemi terminus will continue in 2022. The installation of the overhead cables and finishing touches both on the line and the power supply stations will continue in Espoo in 2022.

In 2023, we will add the finishing touches to the Jokeri Light Rail worksites. We will also run commissioning tests and test traffic. The operation on the light rail should start in January 2024.

Text by Jokeri Light Rail

More information
Jokeri Light Rail webpages

Konemiehentie.jpg

HSY's contstruction site remains in place on Konemiehentie

Exception routes in the Konemiehentie - Sähkömiehentie area will continue until the end of November 2021. Exceptional route arrangements will also remain in place until the site is completed.

Kartta liikennejärjestelyistä2.jpg

Konemiehentie between Puumiehenkuja - Sähkömiehentie is closed until the end of November 2021.

  • Updated:
  • Published:
Share
URL copied!

Read more news

Sustis champparit
Awards and Recognition, Campus Published:

What makes a campus more sustainable? Celebrating 10 years of campus sustainability champions!

Otakargo was chosen as the Campus Sustainability Champion in 2026.
Person in pink pig costume and older man high-five while riding exercise bikes indoors
Campus, Cooperation, University Published:

The Aalto community cycled for 10 hours and welcomed a €10,000 donation for student innovation grants

Aalto University's community drive brought people together to pedal an exercise bike for 10 hours in support of students.
Irving Wang's picture
Campus, University Published:

"You do not need to have everything figured out before you start."

Irving Wang was the winner of the Slush ticket raffled among the 100STARTUPS event participants. We interviewed him to learn more about him and how the event benefited him.
Brick building facade with abstract brick and metal sculpture forming a semicircle around a yellow centre.
Campus, University Published:

Aino’s Embrace celebrates Aalto’s benefactors and Otaniemi’s unique heritage

The artwork honours Aalto University’s donors and draws on Otaniemi’s architectural tradition of joining together the recycling and the reuse of materials.