Construction of Jokeri Light Rail 75% complete – rail construction progressing ahead of schedule
![Raide-Jokeri](/sites/g/files/flghsv161/files/styles/1_6_567w_354h_n/public/2021-11/DJI_0013.jpg?h=a141e9ea&itok=bmp2-kBg)
Of the construction of Jokeri Light Rail, 75 per cent is now completed. We reached the milestone of three quarters at the end of October 2021. Rail construction has progressed ahead of schedule, and 21 kilometres of the 25-kilometre rails are now finished.
The original target was having completed 20 kilometres of the rails by the end of 2021. Expectations were exceeded thanks to successful resourcing, coordination of schedules, and developing working methods. Most of the construction in the Espoo section will be completed in 2021, while the construction of the Keilaniemi terminus will continue in 2022. The installation of the overhead cables and finishing touches both on the line and the power supply stations will continue in Espoo in 2022.
In 2023, we will add the finishing touches to the Jokeri Light Rail worksites. We will also run commissioning tests and test traffic. The operation on the light rail should start in January 2024.
Text by Jokeri Light Rail
More information
Jokeri Light Rail webpages
![Konemiehentie.jpg](/sites/g/files/flghsv161/files/styles/1_6_567w_354h_n/public/2021-11/Konemiehentie.jpg?h=81a3771e&itok=MG9Ke_it)
HSY's contstruction site remains in place on Konemiehentie
Exception routes in the Konemiehentie - Sähkömiehentie area will continue until the end of November 2021. Exceptional route arrangements will also remain in place until the site is completed.
![Kartta liikennejärjestelyistä2.jpg](/sites/g/files/flghsv161/files/styles/1_6_567w_354h_n/public/2021-11/Kartta%20liikenneja%CC%88rjestelyista%CC%882.jpg?h=827069f2&itok=MbXEMM04)
Konemiehentie between Puumiehenkuja - Sähkömiehentie is closed until the end of November 2021.
Read more news
![blueberry](/sites/g/files/flghsv161/files/styles/2_3_288w_125h_d/public/2024-07/WhatsApp-Image-2024-07-18-at-18.21.01.jpeg?h=404059e4&itok=ZxP5IXRY)
A! Walk-Nature connection: Walk, pick, discuss
The afternoon adventure on Lehtisaari offered more than just a walk in the forest; it sparked conversations about renewed appreciation for the simple pleasures of life and the beauty of the Finnish wilderness...![Natural dyes are being presented to the princess.](/sites/g/files/flghsv161/files/styles/2_3_288w_125h_d/public/2024-07/Aalto_University_visit_of_HRH_Sirindhorn_Princess_of_Thailand_26-6-2024_photo_by_Mikko_Raskinen_009.jpg?h=41f55a5b&itok=6jpXJz89)
HRH Princess Maha Chakri Sirindhorn of Thailand visited Aalto University
During the visit, HRH and her delegation met with Aalto students and explored various activities.![Ahomansikka](/sites/g/files/flghsv161/files/styles/2_3_288w_125h_d/public/2024-07/ahomansikka.jpg?h=69d4e0a4&itok=X8D6Z4Gn)
Campus for people, plants and pollinators
The Otaniemi campus nature is managed with respect to biodiversity and the characteristic species of habitats.![Two students at Aalto University campus.](/sites/g/files/flghsv161/files/styles/2_3_288w_125h_d/public/2024-07/Aalto_University_Squad_students_May-2023_by_Aleksi_Poutanen_4895.jpg?h=41f55a5b&itok=-dw6wp5M)