Robust AV - planned renovation projects for 2022

In the Robust AV project, the AV systems of Aalto University's teaching facilities will be renewed and updated. These updates enable lecture capture and remote lectures in the facilities. Based on the site surveys carried out in the premises of the various buildings on the campus, these facilities were selected (list below). AV system upgrades are planned to be carried out during 2022. The criteria for renewing are e.g. outdated presentation technology or the need for an upgrade to support the making of lecture recordings and remote lectures (the so-called hybrid model).

Robust AV - year 2022 AV renovation preliminary plan

  Building Space Time Status
1 Tietotekniikka T2 C105 2022 (vk 2 - 3) in working order
2 Tietotekniikka  T1 C202 2022 (vk 2 - 3) in working order
3 Kone Kone 216 2022 (vk 4 - 5) in working order
4 Kemia Kemia A304 Ke2 2022 (vk 3 - 4) in working order
5 Maarintie 8 2006 AS2 2022 (vk 4 - 5) in working order
6 Maarintie 8 TU1 1018 2022 (vk 4 - 5) in working order
7 Kemia Kemia A305 Ke1 2022 (vk 5 - 6) in working order
8 Kone Kone 215 2022 (vk 5 - 6) in working order
9 Maarintie 8 TU2 2005 2022 (vk 6 - 7) in working order
10 Otakaari 1 Y313 2022 (vk 6 - 7) in working order
11 Kone Kone 401 2022 (vk 10) in working order
12 Maarintie 8 1592 2022 (vk 10) in working order
13 Maarintie 8 1593 2022 (vk 10) in working order
14 Otakaari 1 U271 U9 2022  in working order
15 Otakaari 1 U503 2022 (vk 10 - 11) in working order
         
19 Kone Kone 213a 2022 (vk 13 - 14) in working order
20 Otakaari 1 Y342a 2022 (vk 13 - 14) in working order
21 Otakaari 1 Y344 2022 (vk 14 - 15) in working order
22 Otakaari 1 Y346 2022 (vk 14 - 15) in working order
23 Otakaari 1 Y338 2023 rescheduled
24 Otakaari 1 Y347 2022 (vk 15 -  16) in working order
25 Otakaari 1 Y405 2023 moved to 2023
26 Otakaari 1 A034 2022 (vk 16 - 17) in working order
27 Otakaari 1 A046 2022 (vk 16 - 17) in working order
28 Otakaari 1 A046a 2022 (vk 17 - 18) in working order
29 Otakaari 1 M134 2023  
30 Otakaari 1 M203 2023  
31 Otakaari 1 M205 2023  
32 Otakaari 1 M237 2023  
33 Otakaari 1 M240 2023  
34 Otakaari 1 U115a 2023  
35 Otakaari 1 U121a S-Ryhmä 2023  
36 Otakaari 1 U121b EY 2023  
37 Otakaari 1 U135a U7 2023 rescheduled
38 Otakaari 1 U141 U3 2022 (vk 23 - 24) in working order
39 Otakaari 1 U142 U4 2022 (vk 24 - 25) in working order
40 Otakaari 1 U147 U5 2022 (vk 24 - 25) in working order
41 Otakaari 1 U149 U6 2022 (vk 28 - 29) in working order
42 Otakaari 1 U154 U1 2022 (vk 28 - 29) in working order
43 Otakaari 1 U157 U2 2023 rescheduled
44 Otakaari 1 U250a 2023  
45 Otakaari 1 U256 2023  
46 Otakaari 1 U261 2023  
47 Otakaari 1 U262 2023  
48 Otakaari 1 U264 K-Ryhmä 2023  
49 Otakaari 1 U270 U8 2023 rescheduled
50 Otakaari 3 F175a 2023  
51 Otakaari 3 F175b 2023  
52 Maarintie 8 1174-1176 TU4 2022 (vk 31 -32)  
53 Kone Kone 150 2022 (vk 32 - 33) in working order
54 Maarintie 8 TU5 1194 2022 (vk 33 - 34) in working order
55 Maarintie 8 1199 TU6 2022 (vk 35 - 36) in working order
56 Otakaari 5 A208d Jeti 2023  
57 Maarintalo Maari A 2023 rescheduled
58 Maarintalo Maari C 2023 rescheduled
59 Maarintalo B182 Linux 2023 rescheduled
60 Maarintalo Maari E229 2023 rescheduled
        updated: 6.9.2022

 * list is updated irregularly